Water Treatment Facility - Phase 1

Water Treatment Facility – Phase 1 closed in December 2023. Please refer to our water treatment project page for all details. https://townoflakeview.org/water-treatment-facility/

1)      The Town did not receive a check for the awarded $15,000,000 from project funding through the American Rescue Plan Act (ARPA) program. The Town receives funding via a reimbursement process through Business Oregon. The Town pays for water treatment project items/expenses, and then submits for reimbursement. Please refer to Budget Schedule 2.1.1 to see what has been spent thus far for Phase 1. https://townoflakeview.org/wp-content/uploads/2023/12/Phase-I-TC-12-12-2023.pdf

Grant and Reimbursement Process: https://townoflakeview.org/2023/09/grant-and-reimbursement-process/

2)      Phase 1 – PRE-DESIGN REPORT FOR WATER SYSTEM IMPROVEMENTS
https://drive.google.com/file/d/14lOcOD1ugAxU3eq1g1w43I72N9_HNwXJ/view?usp=sharing
This is a 367-page document that outlines and details what all has been completed in Phase 1.

3)      A timeline and budget for Phases 2 & 3 are currently being worked on by Anderson Perry & Associates, it will be available in February. We will add this to our website and share the details once we receive it.

4)      SAVE THE DATE – State of the Town – Public Special Session Meeting

This meeting will give an update on all Town projects. Water Treatment Facility, Well Rehab, Water Rate Study, Geothermal, URA, Housing Initiative, Smart Meters, and Robert Road.
We encourage you to attend and ask questions.

Date: February 27, 2024
Time: 5:00 PM
Location: Memorial Hall, Basement – 513 Center St., Lakeview, OR 97630

Comments are closed.